Thursday, April 05, 2007

Septic system in, sheetrock about done

.
I got a surprise when I got to the house this morning - the septic system had been installed! Because of the future location of the subgrade power and telephone lines, the builder wrapped the septic system to the south instead of going due east, as previously planned. This picture is looking north from the drywells to the septic tank. Only 3 drywells were required, but the connectors allow for up to 4 and we could put 4 in with the allowance our builder had put aside for this part of the project. Having 4 wells instead of 3 definitely cannot hurt.
.

.
As you can see, all the sheetrock is just about installed. There are still some plugs/switches they have to cut out, but I think they will be taping as soon as tomorrow. And yes, they did finish off the last bit of the garage they had left bare.
.
Most of the windows look almost like gun slits right now, as they have not trimmed the sheetrock back to the window frames yet.
.